|
Case Study:
Tyco Electronics, Rock Hill, SC
May – August 2003
Original Condition
Tyco Electronics, Rock Hill, SC purchases the specified core pin
between $47 and $100 each from suppliers as follows:
|
Supplier
Identification |
Lead Time |
Single Piece Price |
|
USA #1 |
6 weeks |
$75.00 |
|
USA #2 |
5 weeks |
$60.00 |
|
USA #3 |
5 weeks |
$70.00 |
|
USA #4 |
4 weeks |
$63.00 |
|
USA #5 |
4 weeks |
$60.00 |
|
SINGAPORE |
8 weeks |
$50.00 |
|
CHINA |
9 weeks |
$47.00 |
IMP
Assistance
The
challenge for this project is to create a new manufacturing process
using the high technology and technical experts from the Institute for
Manufacturing Productivity’s industry partners that will allow
manufacturing to remain in the United States. That is, competing with
offshore manufacturing in PRICE, Quality, and Delivery.
Critical tolerances of this part are + 20 millionths of an
inch.
Tyco
Electronics registered one student, a senior machinist, in the IMP-501
Process Development continuing education class. The team members were
Tom Dickerson, P.E.-YTC, Bud Rushin-Charmilles
Technologies, Tim Eagen-Tyco Electronics,
Richard Howard-Sandvik, William Beaver,
P.E., M.B.A.-YTC. Note: Bud
Rushin and Richard Howard are application
engineers from industry partners of the Institute for Manufacturing
Productivity (IMP).
The
team established a new manufacturing process in six days documented on
the attached report.
-
The
first 10 pieces were made by the entire team,
-
The
next 40 pieces were made solely by Tim Eagen
– the machinist of Tyco Electronics, with William Beaver, P.E.,
M.B.A observing, documenting, and timing the process,
-
The
purpose of having Tim Eagen produce 40
pieces is to assure that technology transfer has occurred from the
IMP to the customer without the assistance of the technical experts,
-
Tyco
Electronics receives all CNC programs, a documented process, and a
fully trained high-skilled worker to begin realizing the economic
benefits of this process development course.

Image of raw material, in-process core pins, and individual finished
product (above)

Finished product (above)
Summary:
Before: Price per
core pin between $47 and $75, from suppliers.
After: Manufacturing per part
cost with new process as follows:
Material cost: $0.015
Labor cost:
$0.897
Machinery
cost: $8.101
TOTAL COST: $9.01
|
Supplier
Identification |
Lead Time |
Single Piece Price |
|
USA #1 |
6 weeks |
$75.00 |
|
USA #2 |
5 weeks |
$60.00 |
|
USA #3 |
5 weeks |
$70.00 |
|
USA #4 |
4 weeks |
$63.00 |
|
USA #5 |
4 weeks |
$60.00 |
|
SINGAPORE |
8 weeks |
$50.00 |
|
CHINA |
9 weeks |
$47.00 |
|
NEW
IMP PROCESS |
5 days |
$9.01 |
Results & Verification of Effectiveness:
“Two stages of coring were
delivered to the company for inspection. The first set of ten (10)
pins verified application and tolerance capability to complete the
project planning and to set a timeline standard. The balance of the
pins was delivered the week of 8/11/03. Inspection results indicated
that all 40 pins met tolerance/manufacturing requirements as specified
by the engineering drawing and group. The total of 50 core pins will
be implemented into the manufacturing process.”
– Tyco
Electronics Management
Synopsis from Tyco
Electronics Management
“The joint venture between the
Institute for Manufacturing Productivity and Tyco Electronics proved
to be beneficial for both organizations. Education was achieved on
both fronts. Capability and cost analysis of the IMP-501 Core Pin
Project identified significant potential for establishing future
projects between academics and industry.” “Thank you to all who
supported this project. We look forward to continuing our venture
with York Tech with future projects.” - Tyco Electronics Management
Economic Impact
Per part cost reduced by $38 to
$66 each. Total economic impact depends on volume. Additionally, the
new process can be applied to the entire family of core pins.
|